A program of work has been put together for the last week in November and the first week in December. The majority of the work will take place in the evening but some work needs to be scheduled during the school day as follows:

Monday 27th November ESL to remove the electrical lighting / services from the existing ceilings and make safe the wiring to the following areas

•             Reception Foyer

•             Reception Office

•             Small Corridor

•             Kitchen

•             Boys Toilet

The ceiling contractors will then remove and replace the suspended ceiling during Tuesday/Wednesday & Thursday of that week.

The lighting technicians will return on Friday 1st December to install new light fitting, the school will take back possession of these areas Monday 4th December 2017

Monday 4th December ESL to remove the electrical lighting / services from the existing ceilings and make safe the wiring to the following area

•             Reception Classroom

•             Corridors adjacent to boy’s toilets

The ceiling contractors will then remove and replace the suspended ceiling during Tuesday/Wednesday & Thursday of that week.

The lighting technicians will  return on Friday 8th December to install new light fitting, the school will take back possession of these areas Monday 11th December 2017

Please detailed implications of the work on the school day in the Newsletter below.